The new car park of the JUMBO store in Corfu
ProjectsRoadworksCar park

Corfu · 2020

Project facts

2 months

Duration of works

Project owner
JUMBO S.A.
Location
Corfu
Project type
Store car park extension
Completed
2020
Construction type
Road base & retaining walls
Scope
Strip-out, earthworks, drainage & sewerage, walls, fencing, kerbs & road base

01 — The challenge

The JUMBO store in Corfu needed more parking. The new area had to be formed on the neighbouring part of the plot, at a different level from the road, and connected to the existing car park in front of the entrance. The works were completed in 2020, in two months.

02 — Our solution

We started with strip-out and the demolition of the old walls, followed by general excavation and fill to form the new levels. We built new walls and retaining walls along the plot boundaries, the fencing, the drainage and sewerage works and the road base. Kerbs were laid along every boundary and island, and the new area was linked to the existing car park by a ramp.

Photography

Construction stages

07 photos

01The store and its car park before the extension (image: Google Earth)
02Retaining walls and fencing along the road
03The new parking bays between the kerbs
04Kerbs and an island in grass-paver blocks
05The connection to the existing car park
06The new car park, completed
07The car park from above after the extension (image: Google Earth)

Technical scope

8 trades,
one contractor

  1. 01Strip-out
  2. 02Wall demolition
  3. 03General excavation & fill
  4. 04Drainage & sewerage works
  5. 05New walls & retaining walls
  6. 06Fencing
  7. 07Kerbs
  8. 08Road base

The outcome

A new car park beside the JUMBO store in Corfu, completed in 2020 in two months and joined to the existing one, with more spaces for visitors.