Scope of work
Full turnkey construction

01 — The challenge

The client needed a single facility housing coffee production, processing, packaging and distribution without those flows crossing each other. It also had to provide modern administrative offices, a generous yard for truck circulation, and headroom for future capacity expansion.

02 — Our solution

We designed a single 10,000 m² industrial envelope that cleanly separates production from logistics, with long clear spans so machinery can be rearranged without structural work. The 1,500 m² office building was integrated into the main elevation behind a glass curtain wall, loading ramps were placed on the opposite side for independent circulation, and the roof was engineered from the outset to carry a photovoltaic installation covering a substantial share of the facility's energy consumption.

Photography

Construction stages

11 photos

01Earthworks & excavation
02Foundation preparation
03Precast column erection
04Structural frame complete
05Roof & envelope
06Landscaping & site development
07Completed exterior — solar roof & loading ramps
08Interior — production hall
09Interior shell — ready for fit-out
10Pallet racking installation
11The completed facility from above — offices, rooftop solar and landscaped grounds

Technical scope

15 trades,
one contractor

  1. 01Earthworks & excavation
  2. 02Reinforced concrete foundations
  3. 03Structural frame
  4. 04Roofing & thermal insulation
  5. 05Industrial flooring
  6. 06Glass curtain wall
  7. 07Office building
  8. 08Food-grade hygienic panels
  9. 09Fire-rated roller shutters
  10. 10Loading ramps
  11. 11Photovoltaic installation
  12. 12Asphalt paving & parking
  13. 13Stormwater & drainage networks
  14. 14Perimeter boundary walls
  15. 15Landscaping & external works

The outcome

The 11,500 m² facility was handed over fully operational — industrial flooring, food-grade hygienic panels, fire-rated roller shutters, loading ramps, parking areas and landscaped surroundings.

The rooftop photovoltaic installation feeds production, materially reducing the plant's reliance on the grid and its running costs. Remaining open land allows future expansion without interrupting production.

What does a facility like this cost today? The 2026 cost guide
Next project — IndustrialPlayground Manufacturing PlantLagyna, Thessaloniki · 1.200 m²

Next step

Planning a similar project?

Talk to our team — we reply within one business day.